本帖最后由 icy97 于 6-3-2018 05:57 AM 编辑

去年12月赚6亿
国能派息21.41仙


2018年3月1日
(吉隆坡28日讯)国家能源(TENAGA,5347,主板贸易服股)去年12月单月,净赚6亿390万令吉,营业额报42亿2010万令吉,建议派息21.41仙。

从9月1日至12月31日的四个月内,则净赚27亿5570万令吉;营业额报158亿2710万令吉。

董事部已经批准将财年截止日期,从原本的8月31日更改至12月31日,因此业绩无法作出按年比较。

国能持续看好我国今年的经济表现,因此,也预见电力需求能够持稳。

另外,政府持续推行第二期(2018年至2020年)的奖掖基础管制(IBR),也能让公司更准确地预估净利表现,因燃油成本风险已经减少。

董事部相信,2018财年的表现会持稳。【e南洋】

SUMMARY OF KEY FINANCIAL INFORMATION
31 Dec 2017
INDIVIDUAL PERIOD
CUMULATIVE PERIOD
CURRENT YEAR QUARTER
PRECEDING YEAR
CORRESPONDING
QUARTER
CURRENT YEAR TO DATE
PRECEDING YEAR
CORRESPONDING
PERIOD
One Month
One Month
One Month
One Month
01 Dec 2017
To
01 Dec 2017
To
01 Dec 2017
To
01 Dec 2017
To
31 Dec 2017
31 Dec 2017
31 Dec 2017
31 Dec 2017
$$'000
$$'000
$$'000
$$'000
1Revenue
4,220,100
0
15,827,100
47,416,900
2Profit/(loss) before tax
759,100
0
2,979,300
8,281,800
3Profit/(loss) for the period
587,200
0
2,743,900
6,912,100
4Profit/(loss) attributable to ordinary equity holders of the parent
603,900
0
2,755,700
6,904,000
5Basic earnings/(loss) per share (Subunit)
10.67
0.00
48.68
122.00
6Proposed/Declared dividend per share (Subunit)
21.41
0.00
21.41
61.00


AS AT END OF CURRENT QUARTER
AS AT PRECEDING FINANCIAL YEAR END
7
Net assets per share attributable to ordinary equity holders of the parent ($$)
10.0960
10.0920

回复

使用道具 举报


ADVERTISEMENT

发表于 5-3-2018 02:25 AM | 显示全部楼层
本帖最后由 icy97 于 8-3-2018 04:42 AM 编辑

4.18亿入股2公司
国能进军英国风力发电


2018年3月2日
(吉隆坡1日讯)国家能源(TENAGA,5347,主板贸易服股)以7737万英镑(约4.18亿令吉)收购英国两家再生能源公司的80%股权,首次进军该国岸内风力发电市场。

国能今天发文告宣布,独资子公司国能Wind Ventures英国有限公司,已完成收购GVO Wind和Bluemerang资本有限公司80%股权。

这是国能第二次在英国收购,该公司在去年收购Vortex Solar太阳能光伏资产。

根据文告,这项收购是配合国能5年国际发展蓝图而进行,也符合扩展再生能源市场的策略,让国能在2025年成为全球顶尖公用事业公司之一。

国能有意通过新建发展或通过收购其他再生能源资产或互补技术,把再生能源资产组合扩大到最理想的规模。

完成收购之后,国能的国际再生能源资产组合,将会有合计净发电量约280兆瓦。

属低风险投资

国能总裁兼总执行长拿督斯里阿兹曼指出:“这项收购将扩大国能的再生能源资产组合规模,且加强在这市场的技术和商业洞察力。”

这两家英国公司合计资产组合,为英国最大型的电力回购风力发电资产,包括53个岸内中型风力涡轮机,总发电量为26.1兆瓦。

国能收购营运中的风力资产是一项低风险投资,因不会面对策划和建筑风险。

此外,收购的风力资产包括较新的资产,平均为2.5年,且预计可用超过25年。

这些资产遍布英国,提供多元化及对个别岸内风力涡轮机营业额风险作出自然护盘。

同时,也获得当地20年电力回购扶持,并提供诱人的回酬及增值盈利。

配合这项收购,国能有意发展人力资本。国能将促进员工在风力再生能源营运的培训和接触,特别是在一个先进国,因为是最先体验到科技及市场趋势的变化。



周息率上看5%

分析员普遍认为,成本转嫁机制让国能把燃料成本风险转嫁给消费者,而电力需求持续增长约2%至2.9%;盈利展望稳定。

大华继显研究分析员指出:“更重要的是,这表示国能可把大量净利当股息派发给股东。”

昨日,该公司公布4个月业绩表现及建议派息21.41仙,令部分分析员感到意外。

国能已上调股息政策,从2018财年开始,国能将以核心净利的30%至60%用作派息。

派息令人惊喜

加上管理层维持高效资本架构以推动展望,所以分析员认为,周息率会处于较稳定水平,达约5%。

国能去年12月单月,净赚6亿390万令吉,营业额报42亿2010万令吉。

而从9月1日至12月31日的四个月内,则净赚27亿5570万令吉;营业额报158亿2710万令吉。【e南洋】


Type
Announcement
Subject
OTHERS
Description
ACQUISITION OF 80% EQUITY STAKE IN TWO (2) OPERATIONAL ONSHORE WIND PORTFOLIOS IN UNITED KINGDOM
Tenaga Nasional Berhad wishes to announce that it has today, on 28 February 2018 (UK time)/1 March 2018 (Malaysian time), via its wholly owned subsidiary, Tenaga Wind Ventures UK Ltd (“Tenaga Wind”), completed its acquisition of an 80% interest in two (2) United Kingdom (“UK”) renewable energy companies; GVO Wind Limited and Bluemerang Capital Limited (the “Acquired Cos.”) for a cash equity consideration of GBP77.37 million through two (2) Share Purchase Agreements (“SPAs”) with Georg von Opel and Tanzanite B.V. & Catalin Breaban (“the Sellers”) respectively. The Acquired Cos. own the largest Feed-in Tariff (“FiT”) wind portfolio in the UK, comprising 53 operational onshore medium wind turbines with a total combined capacity of 26.1MW.

Tenaga Wind has also today entered into two (2) Shareholders’ Agreements (“SHAs”) with Georg von Opel and Tanzanite B.V. In addition, Tenaga Wind and Longspur Capital Limited (“Longspur Capital”), a renewable energy infrastructure asset manager have entered into Investment Management Agreements (the “IMA”) relating to the management of the Acquired Cos. and its respective portfolio. Longspur Capital is manned by experienced personnel from both Temporis Capital Ltd and Bluemerang Capital Ltd, former asset managers of the Acquired Cos.

Please refer to the attachment for details of the Acquisition.
http://www.bursamalaysia.com/market/listed-companies/company-announcements/5708885

回复

使用道具 举报

发表于 5-3-2018 02:47 AM | 显示全部楼层
本帖最后由 icy97 于 5-3-2018 05:54 AM 编辑

国家能源
风力发电互补佳


2018年3月3日

分析 :达证券
目标价:18.22令吉

最新进展:

国家能源(TENAGA,5347,主板贸易服股)以7737万英镑(约4.18亿令吉),收购英国两家再生能源公司的80%股权,首次进军该国岸内风力发电市场。  

完成收购之后,国能的国际再生能源资产组合,将会有合计净发电量约280兆瓦。

行家建议:

我们正面看待,通过引入更多先进再生能源技术,国能将可多元化旗下发电业务组合。

同时,国能此次收购的是低风险高素质资产,预计还有25年寿命。

另外,这些资产也有英国政府一项长达20年的再生能源机制支持。

另一方面,风力发电一般会在冬季时带来更多营收,而太阳能资产则是在夏季时最具生产效率。因此,这项两项收购的资产可形成互补。

不过,收购价相等于每兆瓦370万英镑,相当昂贵。

然而,国能财务稳健,负债率0.6倍,还有50亿令吉现金,要筹够资金应绰绰有余。



【e南洋】




风电资产贡献不显著.国能财测评级维持


(吉隆坡2日讯)国家能源(TENAGA,5347,主板贸服组)以7737万英镑(4.178亿令吉)收购英国两家风力发电公司,分析员一致认为该风电资产贡献不显著,维持财测与评级。

MIDF研究认为收购不见得廉宜,不过获得英国保证电费达20年。英国2013至2015年所建风力发电场成本每兆瓦350万至410万英镑之间,国家能源所购上述资产大约660万英镑,价位略高。

闭市时,国家能源股价以15令吉70仙平盘价挂收。

上述两项收购再添26兆瓦,使再生能源的国际电能增至280兆瓦。

大众研究也预期上述风力发电资产的贡献不显著,因此维持财测。每兆瓦获223英镑的营收,远比英国与欧洲再生能源电费高。

国家能源是透过旗下国能风电创投英国公司,收购GVO风电公司和Bluemerang资本公司80%股权。

早前则收购Vortex太阳能投资公司50%股权。

分析员说,最新收购的风电资产与太阳能发电资产相辅相成,Vortex将发365兆瓦电力。

MIDF说,风电在冬天时创造更多营收,太阳能资产则在夏天有更高营收。

文章来源:
星洲日报‧财经‧报道:张启华‧2018.03.03
回复

使用道具 举报

发表于 10-3-2018 06:32 AM | 显示全部楼层
本帖最后由 icy97 于 13-3-2018 07:51 AM 编辑
icy97 发表于 15-12-2017 07:50 AM
国能进军智能家居业务

2017年12月9日
(吉隆坡8日讯)国家能源(TENAGA,5347,主板贸易服股)将以2800万令吉,收购资讯工艺服务提供商Setia Haruman Technology私人有限公司(简称SHTECH)的全数股权,借此拓 ...

國能完成2800萬新收購

2018年3月08日
(吉隆坡8日訊)國家能源(TENAGA,5347,主要板貿服)完成以2800萬令吉現金,全購Setia Haruman科技私人有限公司股權。

國能發文告指出,基于履行與Setia Haruman私人有限公司之間有條件股權買賣協議的所有先決條件。

因此,國能也已通過內部融資,完成收購Setia Haruman科技,后者將成為國能獨資子公司。

Setia Haruman科技主要涉及資訊科技(IT)相關服務。

是項股權收購符合國能“Reimagining Tenaga”戰略,即帶動戰略服務產品的進一步增長。

在“Reimagining Tenaga”戰略下,國能將接觸精明電錶(Smart Meter)、智能家居、工業及城市等多項服務。【中国报财经】

Type
Announcement
Subject
OTHERS
Description
PROPOSED ACQUISITION OF 100% EQUITY INTEREST IN SETIA HARUMAN TECHNOLOGY SDN. BHD. ("SHTECH") FOR A CASH CONSIDERATION OF RM28.0 MILLION ("PROPOSED ACQUISITION")
Unless otherwise stated, the abbreviations and definitions used throughout this announcement shall bear the same as those defined in the Announcement.

We refer to the announcement dated 8 December 2017 ("Announcement").

Tenaga Nasional Berhad wishes to announce that the Proposed Acquisition has been completed on 8 March 2018 in accordance with the terms and conditions of the Conditional Sale and Purchase Agreement.

This announcement is dated 8 March 2018.

回复

使用道具 举报

发表于 11-3-2018 02:58 AM | 显示全部楼层
Type
Announcement
Subject
OTHERS
Description
EXTENSION OF SERVICE CONTRACT OF TNB'S PRESIDENT/CHIEF EXECUTIVE OFFICER
Tenaga Nasional Berhad ("TNB") wishes to announce the service contract of Datuk Seri Ir. Azman bin Mohd as President/Chief Executive Officer of TNB has been extended for another two (2) years with effect from 1 July 2018 to 30 June 2020.

This announcement is dated 9 March 2018.

回复

使用道具 举报

发表于 14-3-2018 07:16 AM | 显示全部楼层
料全马最大 工程完成逾半  
太阳能电站11月营运


2018年3月12日
(雪邦11日讯)由国家能源公司(TNB)承建,预计为全马最大的大型太阳能项目,自2017年7月动工以来,已完成50%以上。

这项50兆瓦太阳能电站工程进展顺利,包括安装太阳能电池板、132kv地下电缆及铺设10公里光纤。

国家能源公司(能源投资业务)副总裁拿督诺阿兹曼发文告说,国能将致力于建设132kV变电站及电力控制室,而安装超过23万8000块太阳能电池板的工作正全面展开。

他强调,国能有信心在今年11月如期投入商业营运。

据悉,上述大型太阳能项目是由国能独资子公司—国能雪邦太阳能私人有限公司在瓜拉冷岳一片98公顷的土地上进行,此项目的主要承包商为国能工程有限公司。

国能在去年经过竞争性招标后,赢得这项价值超过3亿令吉的工程,放眼引领国内可再生能源增长,并通过绿色技术优化发电。【e南洋】
回复

使用道具 举报

Follow Us
发表于 20-3-2018 02:07 AM | 显示全部楼层
TENAGA NASIONAL BHD

EX-date
04 Apr 2018
Entitlement date
06 Apr 2018
Entitlement time
04:00 PM
Entitlement subject
Final Dividend
Entitlement description
Final single-tier dividend of 21.41 sen per ordinary share for the Financial Period ended 31 December 2017
Period of interest payment
to   31 Dec 2017
Financial Year End
31 Dec 2017
Share transfer book & register of members will be
to   closed from (both dates inclusive) for the purpose of determining the entitlement
Registrar or Service Provider name, address, telephone no
Symphony Share Registrars Sdn. Bhd.Level 6, Symphony HousePusat Dagangan Dana 1 Jalan PJU 1A/4647301 Petaling JayaSelangor Darul EhsanMalaysiaTel.: 603-7849 0777Fax: 603-7841 8151/8152
Payment date
19 Apr 2018
a.Securities transferred into the Depositor's Securities Account before 4:00 pm in respect of transfers
06 Apr 2018
b.Securities deposited into the Depositor's Securities Account before 12:30 pm in respect of securities exempted from mandatory deposit

c. Securities bought on the Exchange on a cum entitlement basis according to the Rules of the Exchange.
Number of new shares/securities issued (units) (If applicable)

Entitlement indicator
Currency
Currency
Malaysian Ringgit (MYR)
Entitlement in Currency
0.2141

回复

使用道具 举报

发表于 20-3-2018 02:24 AM | 显示全部楼层
本帖最后由 icy97 于 20-3-2018 06:30 AM 编辑

签2份太阳能购电协议 国能派息21.41仙
Neily Syafiqah Eusoff/theedgemarkets.com
March 19, 2018 20:46 pm +08

(吉隆坡19日讯)国家能源(Tenaga Nasional Bhd)与得标者成立的特殊用途公司签署两份大型太阳能购电协议。

根据文告,这两个得标者是位于吉打Kuala Muda的国能厂房及Gebeng私人有限公司位于彭亨关丹的厂房。

这两家特殊用途公司将分别设计、建设、拥有、营运和维护太阳能光伏发电厂。

国能Bukit Selambau Solar私人有限公司的厂房将拥有30兆瓦(MWac)产能,Gebeng的厂房产能则是29.92兆瓦。它们预计,分别在2020年12月31日及2月3日投入运作。

国能说:“签署上述购电协议将不会显著影响国能的发行股本及大股东股权架构,而且将在协议期限内,为国能的收益带来温和的贡献。”

另外,国能宣布,将在截至2017年12月杪财年派发每股21.41仙终期股息,将于4月19日支付,除权日为4月4日。

(编译:魏素雯)

Type
Announcement
Subject
OTHERS
Description
SIGNING OF TWO (2) LARGE-SCALE SOLAR PHOTOVOLTAIC POWER PURCHASE AGREEMENTS BY TENAGA NASIONAL BERHAD WITH EACH OF THE FOLLOWING PARTIES:(i)    TNB BUKIT SELAMBAU SOLAR SDN. BHD.(ii)   RE GEBENG SDN. BHD.
Tenaga Nasional Berhad (“TNB”) refers to the Large-Scale Solar (“LSS”) competitive bidding exercise organised by Suruhanjaya Tenaga in the first quarter of 2017 to develop, among others, the transmission-connected LSS projects.

In relation to the above, TNB wishes to announce that it has today signed two (2) LSS Photovoltaic Power Purchase Agreements (“PPAs”) with special purpose companies (“SPCs”) set up by the successful bidders as listed below:
No.Successful BiddersSPCCapacity (Mwac)
Proposed Location
Scheduled Commercial Operation Date ("SCOD")
1.Tenaga Nasional BerhadTNB Bukit Selambau Solar Sdn. Bhd.30Kuala Muda, Kedah31 December 2020
2.RE Gebeng Sdn. Bhd.RE Gebeng Sdn. Bhd.29.916Kuantan, Pahang3 February 2020
Each of the SPCs will design, construct, own, operate and maintain a solar photovoltaic energy generating facility with the approved capacity (“Facility”) at its proposed location.

The PPAs govern the obligations of the Parties to sell and purchase the energy generated by the Facility for a period of 21 years from the commercial operation date in accordance with the agreed terms and conditions.

The signing of the PPAs will not have any effect on the issued share capital and the substantial shareholders’ shareholdings of TNB and will have a neutral impact on the earnings of TNB over the term of the PPAs.

None of the Directors or Major Shareholders of TNB and/or persons connected with them has any interest, direct or indirect, in relation to the abovementioned PPAs.

This announcement is dated 19 March 2018.

回复

使用道具 举报


ADVERTISEMENT

发表于 28-3-2018 03:55 AM | 显示全部楼层
本帖最后由 icy97 于 31-3-2018 12:42 AM 编辑

Picture6.jpg

Type
Announcement
Subject
OTHERS
Description
SIGNING OF SIX (6) LARGE-SCALE SOLAR PHOTOVOLTAIC POWER PURCHASE AGREEMENTS BY TENAGA NASIONAL BERHAD WITH EACH OF THE FOLLOWING PARTIES:(i)    KENYIR GUNKUL SOLAR SDN. BHD.(ii)   IDIWAN SOLAR SDN. BHD.(iii)  BGMC BRAS POWER SDN. BHD. (iv)  VIVA SOLAR SDN. BHD.(v)   CYPARK ESTUARY SOLAR SDN. BHD.(vi)  COVE SURIA SDN. BHD.
Tenaga Nasional Berhad (“TNB”) refers to the Large-Scale Solar (“LSS”) competitive bidding exercise organised by Suruhanjaya Tenaga in the first quarter of 2017 to develop, among others, the transmission-connected LSS projects.

In relation to the above, TNB wishes to announce that it has today signed six (6) LSS Photovoltaic Power Purchase Agreements (“PPAs”) with special purpose companies (“SPCs”) set up by the successful bidders as listed below:
No.Successful BiddersSPCCapacity (Mwac)
Proposed Location
Scheduled Commercial Operation Date (“SCOD”)
1.Kenyir Solar Park Sdn. Bhd. and Gunkul Engineering Public Co. Ltd.Kenyir Gunkul Solar Sdn. Bhd.29.99Dungun, Terengganu31 December 2019
2.Hasilwan (M) Sdn. Bhd. and Idiqa Holding Sdn. Bhd.Idiwan Solar Sdn. Bhd.30Machang, Kelantan30 September 2020
3.BGMC Corporation Sdn. Bhd. and Bras Venture Bhd.BGMC BRAS Power Sdn. Bhd.30
Kuala Muda, Kedah
30 September 2020
4.Gaya Dunia Sdn. Bhd., Enerta Sdn. Bhd. and Ambang Fiesta Sdn. Bhd.Viva Solar Sdn. Bhd.30Sik, Kedah31 December 2020
5.Revenue Vantage Sdn. Bhd. and Cypark Renewable Energy Sdn. Bhd.Cypark Estuary Solar Sdn. Bhd.30Empangan Terip, Negeri Sembilan31 December 2020
6.Nippon Bumijaya Sdn. Bhd. and B&Z Mechanical and Electrical Sdn. Bhd.Cove Suria Sdn. Bhd.30Empangan Kelinchi, Negeri Sembilan31 December 2020
Each of the SPCs will design, construct, own, operate and maintain a solar photovoltaic energy generating facility with the approved capacity (“Facility”) at its proposed location.

The PPAs govern the obligations of the Parties to sell and purchase the energy generated by the Facility for a period of 21 years from the commercial operation date in accordance with the agreed terms and conditions.

The signing of the PPAs will not have any effect on the issued share capital and the substantial shareholders’ shareholdings of TNB and will have a neutral impact on the earnings of TNB over the term of the PPAs.

None of the Directors or Major Shareholders of TNB and/or persons connected with them has any interest, direct or indirect, in relation to the abovementioned PPAs
.
This announcement is dated 27 March 2018.

回复

使用道具 举报

发表于 29-3-2018 05:38 AM | 显示全部楼层
Type
Announcement
Subject
OTHERS
Description
SIGNING OF LARGE-SCALE SOLAR PHOTOVOLTAIC POWER PURCHASE AGREEMENT BETWEEN TENAGA NASIONAL BERHAD AND KBJ HECMY SDN. BHD.
Tenaga Nasional Berhad (“TNB”) refers to the Large-Scale Solar (“LSS”) competitive bidding exercise organised by Suruhanjaya Tenaga in the first quarter of 2017 to develop, among others, the transmission-connected LSS projects.

In relation to the above, TNB wishes to announce that it has today signed the LSS Photovoltaic Power Purchase Agreement (“PPA”) with a special purpose company, KBJ Hecmy Sdn. Bhd.

KBJ Hecmy Sdn. Bhd. will design, construct, own, operate and maintain a solar photovoltaic energy generating facility of 30MWac to be located in Mukim Chuping, Bukit Keteri, Perlis (“Facility”).

The PPA, which has an expected commercial operation date of 1 December 2020, governs the obligations of the Parties to sell and purchase the energy generated by the Facility for a period of 21 years from the commercial operation date in accordance with the agreed terms and conditions.

The signing of the PPA will not have any effect on the issued share capital and the substantial shareholders’ shareholdings of TNB and will have a neutral impact on the earnings of TNB over the term of the PPA.

None of the Directors or Major Shareholders of TNB and/or persons connected with them has any interest, direct or indirect, in relation to the abovementioned PPA.

This announcement is dated 28 March 2018.

回复

使用道具 举报

发表于 31-3-2018 03:22 AM | 显示全部楼层
本帖最后由 icy97 于 1-4-2018 07:14 AM 编辑

Picture85.png


Type
Announcement
Subject
OTHERS
Description
SIGNING OF LARGE-SCALE SOLAR PHOTOVOLTAIC POWER PURCHASE AGREEMENT BETWEEN TENAGA NASIONAL BERHAD AND REDSOL SDN. BHD.
Tenaga Nasional Berhad (“TNB”) refers to the Large-Scale Solar (“LSS”) competitive bidding exercise organised by Suruhanjaya Tenaga in the first quarter of 2017 to develop, among others, the transmission-connected LSS projects.

In relation to the above, TNB wishes to announce that it has today signed the LSS Photovoltaic Power Purchase Agreement (“PPA”) with Redsol Sdn. Bhd., a special purpose company of the successful bidders, Fumase (Malaysia) Sdn. Bhd. and Scatec Solar Malaysia B.V.

Redsol Sdn. Bhd. will design, construct, own, operate and maintain a solar photovoltaic energy generating facility of 30MWac to be located in Mukim Beriah, Daerah Kerian, Perak (“Facility”).

The PPA, which has an expected commercial operation date of 31 December 2019, governs the obligations of the Parties to sell and purchase the energy generated by the Facility for a period of 21 years from the commercial operation date in accordance with the agreed terms and conditions.

The signing of the PPA will not have any effect on the issued share capital and the substantial shareholders’ shareholdings of TNB and will have a neutral impact on the earnings of TNB over the term of the PPA.

None of the Directors or Major Shareholders of TNB and/or persons connected with them has any interest, direct or indirect, in relation to the abovementioned PPA.

This announcement is dated 30 March 2018.

回复

使用道具 举报

发表于 3-4-2018 04:36 AM | 显示全部楼层
本帖最后由 icy97 于 3-4-2018 06:43 AM 编辑

Picture30.png

Type
Announcement
Subject
OTHERS
Description
TENAGA NASIONAL BERHAD COMPLETES DEBT REFINANCING FOR ITS WIND PORTFOLIO IN THE UNITED KINGDOM
Tenaga Nasional Berhad is pleased to attach its press statement in respect of the abovementioned matter.

This announcement is dated 2 April 2018.
http://www.bursamalaysia.com/market/listed-companies/company-announcements/5743885

回复

使用道具 举报

发表于 26-4-2018 03:00 AM | 显示全部楼层
本帖最后由 icy97 于 7-5-2018 05:57 AM 编辑

国能与Halpro Engineering签21年太阳能购电协议
Emir Zainul/theedgemarkets.com
April 23, 2018 19:24 pm +08

(吉隆坡23日讯)国家能源(Tenaga Nasional Bhd)与Halpro Engineering私人有限公司签署了一份为期21年的大型太阳能光伏购电协议。

Halpro将设计、建造、拥有、营运和维护坐落于彭亨州北根柏巴(Bebar),一座30兆瓦的太阳能光伏发电厂。

国能今日向大马交易所报备,商业营运日预计为2019年12月30日的购电协议,规定双方出售和购买该发电厂的发电量,为期21年。

Halpro是由Majulia私人有限公司和Greencells GMBH成立的特别用途公司,在能源委员会于2017年首季举办的招标活动中,成功竞投传输连接大型太阳能项目。

该协议遵循国能在3月份与Redsol、KBJ Hecmy、Kenyir Gunkul Solar、Idiwan Solar、Viva Sola、Cypark Estuary Solar和Cove Suria私人有限公司等特别用途公司所签署的一系列购电协议。

(编译:陈慧珊)

Type
Announcement
Subject
OTHERS
Description
SIGNING OF LARGE-SCALE SOLAR PHOTOVOLTAIC POWER PURCHASE AGREEMENT BETWEEN TENAGA NASIONAL BERHAD AND HALPRO ENGINEERING SDN. BHD.
Tenaga Nasional Berhad (“TNB”) refers to the Large-Scale Solar (“LSS”) competitive bidding exercise organised by Suruhanjaya Tenaga in the first quarter of 2017 to develop, among others, the transmission-connected LSS projects.

In relation to the above, TNB wishes to announce that it has today signed the LSS Photovoltaic Power Purchase Agreement (“PPA”) with Halpro Engineering Sdn. Bhd., a special purpose company set up by the successful bidders, comprising of Majulia Sdn. Bhd. and Greencells GMBH.

Halpro Engineering Sdn. Bhd. will design, construct, own, operate and maintain a solar photovoltaic energy generating facility of 30MWac to be located in Mukim Bebar, Daerah Pekan, Pahang (“Facility”).

The PPA, which has an expected commercial operation date of 30 December 2019, governs the obligations of the Parties to sell and purchase the energy generated by the Facility for a period of 21 years from the commercial operation date in accordance with the agreed terms and conditions.

The signing of the PPA will not have any effect on the issued share capital and the substantial shareholders’ shareholdings of TNB and will have a neutral impact on the earnings of TNB over the term of the PPA.

None of the Directors or Major Shareholders of TNB and/or persons connected with them has any interest, direct or indirect, in relation to the abovementioned PPA.

This announcement is dated 23 April 2018.

回复

使用道具 举报

发表于 11-5-2018 01:51 AM | 显示全部楼层
Picture10.png
回复

使用道具 举报

发表于 13-5-2018 04:50 AM | 显示全部楼层
Picture38.png
回复

使用道具 举报

发表于 20-5-2018 04:57 AM | 显示全部楼层
Picture19.png
回复

使用道具 举报


ADVERTISEMENT

发表于 28-5-2018 05:59 AM | 显示全部楼层
本帖最后由 icy97 于 3-6-2018 06:10 AM 编辑

Picture17.png

SUMMARY OF KEY FINANCIAL INFORMATION
31 Mar 2018
INDIVIDUAL PERIOD
CUMULATIVE PERIOD
CURRENT YEAR QUARTER
PRECEDING YEAR
CORRESPONDING
QUARTER
CURRENT YEAR TO DATE
PRECEDING YEAR
CORRESPONDING
PERIOD
31 Mar 2018
31 Mar 2017
31 Mar 2018
31 Mar 2017
$$'000
$$'000
$$'000
$$'000
1Revenue
12,274,000
0
12,274,000
0
2Profit/(loss) before tax
2,415,400
0
2,415,400
0
3Profit/(loss) for the period
2,116,800
0
2,116,800
0
4Profit/(loss) attributable to ordinary equity holders of the parent
2,119,700
0
2,119,700
0
5Basic earnings/(loss) per share (Subunit)
37.41
0.00
37.41
0.00
6Proposed/Declared dividend per share (Subunit)
0.00
0.00
0.00
0.00


AS AT END OF CURRENT QUARTER
AS AT PRECEDING FINANCIAL YEAR END
7
Net assets per share attributable to ordinary equity holders of the parent ($$)
10.2018
10.0764

回复

使用道具 举报

发表于 3-6-2018 06:49 AM | 显示全部楼层
Picture42.png
回复

使用道具 举报

发表于 17-6-2018 05:30 AM | 显示全部楼层
Picture34.png
回复

使用道具 举报

发表于 21-6-2018 03:02 PM | 显示全部楼层
连续跌了整个星期。。。 今天终于跌破 RM14。。。到 RM13.60 了。
就看看下午可否爬回去 14 了。

:-/

:-(
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 注册

本版积分规则

 

ADVERTISEMENT



ADVERTISEMENT



ADVERTISEMENT

ADVERTISEMENT


版权所有 © 1996-2023 Cari Internet Sdn Bhd (483575-W)|IPSERVERONE 提供云主机|广告刊登|关于我们|私隐权|免控|投诉|联络|脸书|佳礼资讯网

GMT+8, 16-4-2024 03:34 PM , Processed in 0.061161 second(s), 25 queries , Gzip On.

Powered by Discuz! X3.4

Copyright © 2001-2021, Tencent Cloud.

快速回复 返回顶部 返回列表